Cases Decided in the Court of Claims of the United States, Volume 105U.S. Government Printing Office, 1946 - Law reports, digests, etc |
From inside the book
Results 1-5 of 100
Page 32
... additional cost to the Government . Some time during the spring of 1935 the contracting officer decided to construct Grand Coulee Dam to its full height and discussed a change order with plaintiffs . On June 5 , 1935 , a change order ...
... additional cost to the Government . Some time during the spring of 1935 the contracting officer decided to construct Grand Coulee Dam to its full height and discussed a change order with plaintiffs . On June 5 , 1935 , a change order ...
Page 33
... Additional information having become available it is found desirable , in pursuance of the provisions of Ar- ticle 4 of the contract with you dated July 16 , 1934 ( Symbol No. 1-2r - 4359 ) , and in pursuance of the pro- visions of ...
... Additional information having become available it is found desirable , in pursuance of the provisions of Ar- ticle 4 of the contract with you dated July 16 , 1934 ( Symbol No. 1-2r - 4359 ) , and in pursuance of the pro- visions of ...
Page 44
... additional claims be sent directly to the contracting officer . On December 21 , counsel replied that plaintiffs had not in terms invoked Article 15 because , in their view , it was " without binding force and effect in respect of the ...
... additional claims be sent directly to the contracting officer . On December 21 , counsel replied that plaintiffs had not in terms invoked Article 15 because , in their view , it was " without binding force and effect in respect of the ...
Page 45
... additional claims , and additional details in support of the claims previously filed , were filed with the contracting officer . Between March 4 and May 3 statements of the amounts of damages claimed , under all of the claims previously ...
... additional claims , and additional details in support of the claims previously filed , were filed with the contracting officer . Between March 4 and May 3 statements of the amounts of damages claimed , under all of the claims previously ...
Page 55
... additional evidence to court if claim is rejected . - Plaintiff's claim before the Com- missioner for refund of floor - stocks tax , under title VII of the Revenue Act of 1936 , was in the nature of a petition in court , the allegations ...
... additional evidence to court if claim is rejected . - Plaintiff's claim before the Com- missioner for refund of floor - stocks tax , under title VII of the Revenue Act of 1936 , was in the nature of a petition in court , the allegations ...
Other editions - View all
Common terms and phrases
act of March additional agency agreed agreement allotments amended amount appropriated April Article bands borrow pit building change order Cheyenne River Commissioner compensation completion construction contracting officer contractor Corporation cost December deductions defendant defendant's delay Department disbursements dredging entitled to recover excavation expenditures expense February February 28 filed follows furnished Government Grand Ronde Reservation installation Interior January July July 29 June 30 labor land letter liquidated damages Lower Brulé material ment Murch Company November Opinion oysters paid payment percent period permanent fund Pine Ridge Pine Ridge Reservation plaintiff plaster proceed proposal Quonset Point raw silk Rayon refund reimbursement Reporter's Statement requested Rogue River Tribe rolled fill Rosebud Scoton Sioux Tribe South Dakota south of Quonset specifications Standing Rock Reservation Stat stone submitted Surety thereof tion Treasury treaty TRIBE OF INDIANS Umpquas United
Popular passages
Page 475 - Every claim against the United States cognizable by the Court of Claims, shall be forever barred unless the petition setting forth a statement thereof is filed in the court, or transmitted to it by the Secretary of the Senate or the Clerk of the House of Representatives, as provided by law, within six years after the claim first accrues...
Page 137 - ... unforeseeable causes beyond the control and without the fault or negligence of the Contractor, including, but not restricted to, acts of God, or of the public enemy, acts of the Government, in either its sovereign or contractual capacity, a,cts of another contractor in the performance of a contract with the Government, fires, floods, epidemics, quarantine restrictions, strikes, freight embargoes, and unusually severe weather, or delays of subcontractors or suppliers due to such causes...
Page 138 - Contractor charged with liquidated or actual damages, as provided in paragraph (b) hereof because of any delays in the completion of the work due to unforeseeable causes beyond the control and without the fault or negligence of the Contractor, including, but not restricted to, acts of God, or of the public enemy, acts of the Government...
Page 635 - Where at any time the power to revest in the grantor title to any part of the corpus of the trust is vested — (1) in the grantor, either alone or in conjunction with any person not having a substantial adverse interest...
Page 100 - The delay in the completion of the work arises from unforeseeable causes beyond the control and without the fault or negligence of the Contractor...
Page 673 - Court to hear and determine the claims listed on page 678 of the hearings before the subcommittee of the House Committee on Appropriations on the...
Page 101 - Disputes. — Except as otherwise specifically provided in this contract, all disputes concerning questions of fact arising under this contract shall be decided by the contracting officer subject to written appeal by the contractor within 30 days to the head of the department concerned or his duly authorized representative, whose decision shall be final and conclusive upon the parties thereto. In the meantime the contractor shall diligently proceed with the work as directed.
Page 508 - Into lots, and assign the same to such individuals or families of the said confederated tribes as are willing to avail themselves of the privilege, and will locate on the same as a permanent home, on the same terms and subject to the same regulations...
Page 134 - ... the Government may, by written notice to the contractor, terminate his right to proceed with the work or such part of the work as to which there has been delay.
Page 791 - States, to admit amongst them; and the United States now solemnly agrees that no persons except those herein designated and authorized so to do, and except such officers, agents, and employees of the Government as may be authorized to enter upon Indian reservations in discharge of duties enjoined by law, shall ever be permitted to pass over, settle upon, or reside in the territory described in this article...