Page images
PDF
EPUB
[blocks in formation]

acter. They were approved December 11, 1907, and were certified to the State December 18, 1907, and were thereupon conveyed by the State to one who took title for the appellant, who had procured the selection and the certification. These sections require that the indemnity lands to be conveyed thereunder shall not be mineral in character. Only Congress can convey title to the land of the United States, and it makes no difference what was its equitable obligation to convey title under the original grant of 1845 in respect of indemnity lands. Congress certainly intended to convey as indemnity lands only those described in the Act of 1891. There was no power in anyone representing the United States, therefore, to convey indemnity land which was mineral in character; and any scheme by which conveyance of such land was obtained was a fraud upon the United States.

The decree of the Circuit Court of Appeals is

Affirmed.

BARRETT COMPANY v. UNITED STATES.

APPEAL FROM THE COURT OF CLAIMS.

No. 105. Submitted January 7, 1927.-Decided February 21, 1927. 1. After cancellation of a contract under which supplies were to be manufactured for the Government in a plant to be built with government funds and to belong to the Government, the making of a supplemental agreement by which the contractor bought the plant for a price stated did not affect the contractor's claims growing out of the termination of the original contract, when the later agreement was expressly without prejudice to them. P. 232. 2. The just compensation to which a claimant is entitled upon cancellation of a contract by the Government, under the Act of June 15, 1917, is not to be measured by the profit that would have accrued under the contract, but must embrace that value which was taken from the contractor by the termination of the contract. The contractor is to be credited with his outlays reasonably made for the fulfillment of the contract. P. 235.

Opinion of the Court.

273 U.S.

3. In this case, where the obligation of the contractor was to manufacture and furnish to the Government a definite quantity of xylol monthly, up to a specified amount, in a plant which was to be erected by the contractor with government funds and belong to the Government, just compensation, upon cancellation of the contract, must include what the contractor expended on the plant in excess of the cost as estimated and adopted in the contract and paid by the Government, in so far as such additional expenditure was required to fit the plant for production of the xylol as the contract contemplated. P. 234.

60 Ct. Cls. 343, reversed.

APPEAL from a judgment of the Court of Claims in an action to recover under an agreement with the Government for the manufacture of xylol.

Messrs. George A. King and William B. King, with whom Mr. Francis H. McAdoo was on the brief, for the appellant, submitted.

Solicitor General Mitchell for the United States, submitted.

MR. CHIEF JUSTICE TAFT delivered the opinion of the Court.

This is an appeal from the Court of Claims under §§ 242 and 243 of the Judicial Code from a judgment of February 16, 1925, before the effective date of the Act of February 13, 1925, § 14, c. 229, 43 Stat. 936.

The findings of fact by the Court of Claims show that the Barrett Company, the claimant and appellant, a corporation under the laws of New Jersey, entered into a contract with the United States by which it undertook, with funds provided by the Government, to erect a plant at Frankford, Pennsylvania, for the distillation of xylol at the rate of 225,000 gallons per month, and, after completion, to operate the plant until a total of 2,700,000 gallons of xylol had been produced. The xylol was to be distilled and refined from special solvent naphtha fur

227

Opinion of the Court.

nished by the Government, and was at all times to belong to the Navy. The by-products, except what the Navy wished to retain, were to belong to the Barrett Company as part of its profit, but not to be sold without the Navy's written consent. Ninety per cent. of the by-products sold by the company was to be credited to the account of the Navy, less one cent a gallon for rental of containers used for shipment.

The price to be paid by the Navy to the company was to be determined monthly for the preceding month by the actual deliveries, first, by a charge per gallon of xylol prorating the total approved estimated cost of the new plant against the 2,700,000 gallons to be made under the contract. At the same time, the account of the Navy was to be credited with this charge, as the total approved estimated cost would have been advanced by the United States to the company before the production of the xylol would begin. To cover operating cost, there was to be a charge of 3 cents per gallon of naphtha distilled, and an additional charge for redistillation of fractions. These charges were to be multiplied by the gallons of naphtha distilled, and the resulting aggregate was to be divided by the number of gallons produced monthly, to which 6.6 cents per gallon was to be added to cover overhead, profit and use of patents.

The new plant was to be an annex to the appellant's existing distillation plant and equipment. The estimated cost to be furnished by the Government, was to be exhibited to the authorities of the Navy Department for approval, prior to the execution of the contract, and was to consist of two parts. First, there was to be an itemized estimate to cover the cost of the separate unit plant and equipment, and, second, an itemized estimate to cover the cost of parts of the plant and equipment needed. for the supply of electric power, steam, water, and light, which would not be distinctly separate from the existing

[blocks in formation]

plant and equipment of the company. One-half of the sum to be advanced for construction was to be paid by the Government at the time of the execution of the contract, and the balance in two months. Plant and equipment were to be ready for operation within five months from the date of the contract, and to be continued in operation until the company had delivered the full amount of 2,700,000 gallons of xylol to E. I. du Pont de Nemours and Company. The xylol provided for in the contract was to be employed in the manufacture of trinitroxylol, for use in mine barrage in the North Sea, and was a new product requiring knowledge and skill in its manufacture. The plant, when completed, was to belong to the Government. The company agreed to offer and to pay 25 per cent. of the approved estimated cost for it if accepted, after the contract was performed; but the Government could dispose of it as it chose.

It was stipulated in the contract that the Barrett Company should furnish a bond for the faithful performance of the contract, equal to the approved estimate of the cost of construction; that time was an essential element in the contract; that, by failure to make delivery in conformity with the requirements of the contract and within the times prescribed, the United States would be damaged; that the damage should be liquidated for each day's delay at the rate of a certain per cent. of the contract price; and that legal excuse for delays was to be determined by the United States.

The company's estimate for the separate unit and equipment was $192,547.80, and that for the plant for supplying electric power, steam, water and light was $60,773.32, a total of $253,321.12. These estimates were approved by the Navy Department, and one-half of the cost, $126,660.56 was advanced to the plaintiff on the execution of the contract, and the remainder was paid two months thereafter.

227

Opinion of the Court.

On May 18th, 1918, the Navy Department gave notice to the company that it might proceed immediately upon the construction of the plant. It did so, and completed the separate plant at a cost of $284,882.66. The electric, steam, water and light plant had been, at the time of the armistice, about half constructed, at a cost of $52,897.53. The total expenditure on plant and equipment, by the company, was thus $337,780.19, or $84,459 more than the estimates submitted by the plaintiff. The increased cost of construction was due to the increases in the cost of ' labor and materials, and to a change in construction from steel and brick to reinforced concrete and brick, due to inability to secure steel, and to certain changes in the tanks as originally proposed, in order to increase their capacity. None of these changes was either directly authorized or approved by the Navy Department; but it does appear that the Department had knowledge of the changes and made no objection thereto.

After the armistice, November 18, 1918, the Navy Department notified the plaintiff that the manufacture of xylol under the contract should be discontinued; that construction work remaining to be completed under the contract would not be undertaken, and that the fact that the Navy would receive a partly finished plant would be considered in the final adjustment to be made with regard to the contract. The Navy thereafter discontinued further supply of naphtha, and work under the contract was terminated.

The Navy Department, on December 1, 1918, made a supplementary agreement with the company, by which the company bought the whole plant for $110,000. This supplemental contract contained the following: "It is further agreed that this supplementary contract does not prejudice the right of the contractor to secure payment of claims in settlement for the termination of the original contract No. 38925 by the Government.'

« PreviousContinue »