Congressional Serial SetU.S. Government Printing Office, 1911 - United States Reports, Documents, and Journals of the U.S. Senate and House of Representatives. |
From inside the book
Results 1-3 of 33
Page xvii
... Gatun Locks. Testing Stoney Gate valve gates at upper locks, November 19, 1910. 2. Gatun Locks, looking north ... Lake section. 93. Lighting and buoying canal, front range towers for Gatun Lake section and beacons for Culebra Cut and ...
... Gatun Locks. Testing Stoney Gate valve gates at upper locks, November 19, 1910. 2. Gatun Locks, looking north ... Lake section. 93. Lighting and buoying canal, front range towers for Gatun Lake section and beacons for Culebra Cut and ...
Page 37
... Gatun Lake in the vicinity of Gatun, one in an exposed location in the open part of the lake about a thousand feet from shore, the second among the trees near the lake border, and the third in an extensive patch of tall rushes ...
... Gatun Lake in the vicinity of Gatun, one in an exposed location in the open part of the lake about a thousand feet from shore, the second among the trees near the lake border, and the third in an extensive patch of tall rushes ...
Page 38
... Gatun Lake. At the Canoa saddle, near the headwaters of the Trinidad, as reported previously, it will be necessary to construct a dike or wall, and similar work will be required at the headwaters of the Las Guacas Creek, about half a ...
... Gatun Lake. At the Canoa saddle, near the headwaters of the Trinidad, as reported previously, it will be necessary to construct a dike or wall, and similar work will be required at the headwaters of the Las Guacas Creek, about half a ...
Contents
Report of the chairman and chief engineer | 1 |
Report of the chairman and chief engineerContinued Page | 57 |
APPENDIX | 65 |
23 other sections not shown
Other editions - View all
Common terms and phrases
addition Ancon April Atlantic division Back fill Balboa barges caisson canal prism Canal Zone cars cent completed central division Chagres River chain channel charge chief engineer Cocoli connection construction Cristobal cubic yards Culebra Cut culvert density district division cost division engineer dredges drills dry fill dump east elevation ended June 30 equipment erection excavation February fiscal year ending Gamboa Gatun Dam Gatun Lake Gatun Locks Gorgona guard gates handled hour hydraulic fill inches installed Isthmian Canal Commission Isthmus January July June 30 labor linear feet locomotives lower lock machines March miles Miraflores Locks mixers month operation output Pacific division Panama Railroad Pedro Miguel Locks pipe placed Porto Bello pressure pumping relocation removed repairs reservoir rock sand September side slides spillway station steam shovels steel suction dredges tion Toro Point total amount total number track trestle upper lock valves wall yards of material