Congressional Serial SetU.S. Government Printing Office, 1911 - United States Reports, Documents, and Journals of the U.S. Senate and House of Representatives. |
From inside the book
Results 1-3 of 85
Page 290
... Pacific Total It will be seen that the division of general expenses has resulted in a surcharge of 7.85 per cent to the Atlantic division, 10.79 per cent to the central division, and 8.07 per cent to the Pacific division over division ...
... Pacific Total It will be seen that the division of general expenses has resulted in a surcharge of 7.85 per cent to the Atlantic division, 10.79 per cent to the central division, and 8.07 per cent to the Pacific division over division ...
Page 291
When it is considered that the Atlantic and Pacific divisions used nearly all the excavated material in the construction of dams and fills adjacent to the points from which the material was excavated and charged to the work benefited ...
When it is considered that the Atlantic and Pacific divisions used nearly all the excavated material in the construction of dams and fills adjacent to the points from which the material was excavated and charged to the work benefited ...
Page 303
... division 308 Table 3.— Pacific division 308 Exhibit B. — Detailed cost per unit of work, fiscal year 1911: Table 1. — Dry excavation — Atlantic division — Prism 313 Gatun spillway — Excavation 313 Preparing foundations 314 Gatun locks ...
... division 308 Table 3.— Pacific division 308 Exhibit B. — Detailed cost per unit of work, fiscal year 1911: Table 1. — Dry excavation — Atlantic division — Prism 313 Gatun spillway — Excavation 313 Preparing foundations 314 Gatun locks ...
Contents
Report of the chairman and chief engineer | 1 |
Report of the chairman and chief engineerContinued Page | 57 |
APPENDIX | 65 |
23 other sections not shown
Other editions - View all
Common terms and phrases
addition Ancon April Atlantic division Back fill Balboa barges caisson canal prism Canal Zone cars cent completed central division Chagres River chain channel charge chief engineer Cocoli connection construction Cristobal cubic yards Culebra Cut culvert density district division cost division engineer dredges drills dry fill dump east elevation ended June 30 equipment erection excavation February fiscal year ending Gamboa Gatun Dam Gatun Lake Gatun Locks Gorgona guard gates handled hour hydraulic fill inches installed Isthmian Canal Commission Isthmus January July June 30 labor linear feet locomotives lower lock machines March miles Miraflores Locks mixers month operation output Pacific division Panama Railroad Pedro Miguel Locks pipe placed Porto Bello pressure pumping relocation removed repairs reservoir rock sand September side slides spillway station steam shovels steel suction dredges tion Toro Point total amount total number track trestle upper lock valves wall yards of material