Page 65
... erection of the operating machinery at the locks and spillways. In addition, it is responsible for the inspection of the manufacture and of the erection, under contract or otherwise, of certain of the structures and machines designed in ...
... erection of the operating machinery at the locks and spillways. In addition, it is responsible for the inspection of the manufacture and of the erection, under contract or otherwise, of certain of the structures and machines designed in ...
Page 70
... erection of the gates at Gatun January 1 and at Pedro Miguel Marcli 1, 1911. Owing to delays in delivering the material for the gate leaves, the contractors did not begin the actual erection until much later, although their erection ...
... erection of the gates at Gatun January 1 and at Pedro Miguel Marcli 1, 1911. Owing to delays in delivering the material for the gate leaves, the contractors did not begin the actual erection until much later, although their erection ...
Page 117
... ERECTION. Actual gate erection was commenced in May, 1911. This division has not been directly concerned with the gate erection, but has prepared the necessary back fill, storage tracks, and erection tracks for the contractor. Such ...
... ERECTION. Actual gate erection was commenced in May, 1911. This division has not been directly concerned with the gate erection, but has prepared the necessary back fill, storage tracks, and erection tracks for the contractor. Such ...
Contents
Report of the chairman and chief engineer | 1 |
Report of the chairman and chief engineerContinued Page | 57 |
APPENDIX | 65 |
23 other sections not shown
Other editions - View all
Common terms and phrases
addition Ancon April Atlantic division Back fill Balboa barges caisson canal prism Canal Zone cars cent completed central division Chagres River chain channel charge chief engineer Cocoli connection construction Cristobal cubic yards Culebra Cut culvert density district division cost division engineer dredges drills dry fill dump east elevation ended June 30 equipment erection excavation February fiscal year ending Gamboa Gatun Dam Gatun Lake Gatun Locks Gorgona guard gates handled hour hydraulic fill inches installed Isthmian Canal Commission Isthmus January July June 30 labor linear feet locomotives lower lock machines March miles Miraflores Locks mixers month operation output Pacific division Panama Railroad Pedro Miguel Locks pipe placed Porto Bello pressure pumping relocation removed repairs reservoir rock sand September side slides spillway station steam shovels steel suction dredges tion Toro Point total amount total number track trestle upper lock valves wall yards of material