Page 147
... steam shovels during the fiscal year ending June 30, 1911. Work at this point was completed on April 15, 1911. POINT 15. One hundred and twelve thousand two hundred and thirty-eight cubic yards of material were removed at Point 6 by steam ...
... steam shovels during the fiscal year ending June 30, 1911. Work at this point was completed on April 15, 1911. POINT 15. One hundred and twelve thousand two hundred and thirty-eight cubic yards of material were removed at Point 6 by steam ...
Page 152
... STEAM SHOVEL REPAIRS. Since November 5, 1907, the central division has had a force of boilermakers, pipefitters, and machinists, with the necessary helpers, working in the cut at night, repairing steam shovels, and it has been found by ...
... STEAM SHOVEL REPAIRS. Since November 5, 1907, the central division has had a force of boilermakers, pipefitters, and machinists, with the necessary helpers, working in the cut at night, repairing steam shovels, and it has been found by ...
Page 199
... shovel days. . . 14 Average output per steam shovel 3 H 12 1 >5 14 .5 1,912 1,864 1,733 1,582 Output Steam- Total outper steam- shovel put, cross shovel day —Statement showing output of steam shovels on the Gatun- Monte Lirio section of ...
... shovel days. . . 14 Average output per steam shovel 3 H 12 1 >5 14 .5 1,912 1,864 1,733 1,582 Output Steam- Total outper steam- shovel put, cross shovel day —Statement showing output of steam shovels on the Gatun- Monte Lirio section of ...
Contents
Report of the chairman and chief engineer | 1 |
Report of the chairman and chief engineerContinued Page | 57 |
APPENDIX | 65 |
23 other sections not shown
Other editions - View all
Common terms and phrases
addition Ancon April Atlantic division Back fill Balboa barges caisson canal prism Canal Zone cars cent completed central division Chagres River chain channel charge chief engineer Cocoli connection construction Cristobal cubic yards Culebra Cut culvert density district division cost division engineer dredges drills dry fill dump east elevation ended June 30 equipment erection excavation February fiscal year ending Gamboa Gatun Dam Gatun Lake Gatun Locks Gorgona guard gates handled hour hydraulic fill inches installed Isthmian Canal Commission Isthmus January July June 30 labor linear feet locomotives lower lock machines March miles Miraflores Locks mixers month operation output Pacific division Panama Railroad Pedro Miguel Locks pipe placed Porto Bello pressure pumping relocation removed repairs reservoir rock sand September side slides spillway station steam shovels steel suction dredges tion Toro Point total amount total number track trestle upper lock valves wall yards of material